Renovation

July 27, 2020 - The kitchen/cafeteria and lobby areas are coming together nicely at the Winslow Junior High School building addition.

June 2, 2020 - Exterior sitework and pavement taking place and interiors are making great progress at the Winslow Jr. High School Addition.

May 5, 2020 - The Winslow Junior High School project is looking great on the outside and casework and cabinets have been installed on the inside.

April 27, 2020 - Interiors are coming together and HVAC and electrical systems are being installed.

March 31, 2020 - More progress to the exterior of the building.

February 23, 2020 - With the mechanical, plumbing & electrical rough-in well underway, the drywall is starting to be hung. The windows have arrived and are being installed.

February 9, 2020 - Photos show the ongoing interior framing, mechanical, plumbing and electrical rough-ins.

January 26, 2020 - Crews are making progress inside of the Winslow School project by preparing and placing the final section of slab in the classroom wing and starting interior framing.

January 10, 2020 - The crews are making progress on getting the additions closed in. The classroom addition has a tight roof, exterior sheathing with a weather barrier and temporary enclosures at the window and door openings allowing interior work to proceed. The band addition is getting sheathing installed and the cafeteria addition exterior framing is underway.

December 23, 2019 - Classroom wing exterior walls are framed and sheathed and roofing has started getting ready for mechanical rough-in. with the band room close behind, steel frame for the cafeteria has been installed.





December 9, 2019 - These progress photos show the exterior framing and sheathing underway on the classroom wing, and the cafeteria addition is ready for steel.

November 24, 2019 - The progress shown here are foundations being placed for the cafeteria and last foundations of the project; the exterior wall framing started on the classroom addition; and the gymnasium expansion roof structure is complete

November 8, 2019 - Steel has gone up for the classroom and band room areas, foundation prep ongoing for the cafeteria addition, and a new grease trap being installed.

November 1, 2019 - Steel being erected.





October 31, 2019 - Prepping for the slab on grade at the classroom wing including under slab piping, vapor barrier, insulation and reinforcing. Also the roof bar joists have arrived for the gym expansion and the fire wall is being constructed between existing school and classroom addition.

October 10, 2019 - Winslow School Project Update: Masonry for the gymnasium expansion is nearing completion with topping off expected by the end of the week. Underground plumbing at the classroom wing is being installed and foundation at the Band addition is being insulated

Masonry for Gym

Masonry for Gym

Underground Plumbing

Foundation for Band Room Addition

September 26, 2019 - Crews are taking advantage of the weather and have completed the foundation for the classroom wing and are now moving on to the band room addition.

Dirt and the beginnings of a foundation
Backhoe
Construction workers pouring cement into a form